Meeting
Minutes, February 29, 2024
CALL TO ORDER
February 29 @ 5:35 PM
Location: Rick’s House
Members present: Rick Hill, Jonathan Hoy, Amanda Williams
Member at large: None
Neighbors present: None
APPROVAL OF PREVIOUS MONTH MINUTES
* January 23 2024 Minutes approved
FINANCIAL BALANCES
* First Security Bank Checking : $ 1,279.70
* LGIF: $3,053.37
*Cash: $223.96
* Total Funds: $4,557.03
Insurance payment of $1,174.00 was made
in January (paid)
Amanda was reimbursed $154.43 (paid)
Government Ethics Fee $75.66 (Check
signed by two members and will be sent )
LGIP change needed to !st Security
Transfer of $3,000. (Rick reported that this change has occurred automatically
and the funds are in the proper account.)
OLD BUSINESS
*Road Repair Plan 2024
Done so far:
-Asphalt Repair: We have already accomplished a significant
amount of maintenance.
As noted in last month’s notes, we repaired the large
sinking patches near the bridge on Sarkisian on January 23.
-Clear/trim edge of pavement.We have cleared/trimmed the
edges of the pavement on major stretches of both Sarkesian and Powe.
- We have cut back vegetation in several easements.
Still required:
- Trim edges. Sandy remains to be cleared and the remainder of Powe and
Sarkisian.
Further Asphalt Repair:
- Several alligator patches on both Powe and Sarkisian. (Described
in January minutes)
- Aquaphalt 6.0: Rick has researched a newer product called
Aquaphalt 6.0, available through major retail outlets, including Ace Hardware. It
is activated with water and easier to use in wet cold climates. Also may be
easier to apply. The board agreed to try it on one patch to determine how well
it would work for our needs.
Clearing/Cutting back Vegetation:
- Note this task includes disposing of limbs and bushes. The
removal of the material is a major part of the job. In each case we must
determine where we will put the material & how to haul it, before we start
the work party.
- Some easements remain to be cleared including overhanging
branches.
- Hedge along the beach path.
- Clear, maintain stairs to beach. It was noted by Jonathon
that the steps are easily eroded, so careful work on this is required.
- Jonathon also notes that we would like to cut back some of
the bushes/trees blocking the ocean and beach view to the south from our public
viewing bench at the top of the stairway. We discussed the disposal of material
for this task. Not easy to haul out.
- Work Parties. We will plan neighborhood work parties for
the tasks above.
NEW BUSINESS
* The members acknowledged that they have reviewed and are
cognizant of Public Contracting Laws.
* Vector Solutions Contractor to Provide all Training for SDAO.
Rick reported that Vector Solutions has been given the
contract for all training provided and/or required by the Special Districts
Association of Oregon. In the past we have each taken courses required for
various matters, so this impacts us. It is not always easy to access the
training and can be a time consuming task.
Rick reported the training site offered by Vector Solutions
appears to be as time consuming as in the previous site, and possibly worse.
NEXT MEETING:
*March 14 @ TBD
ADJOUNMENT:
*6:30pm